Timetable & Process The timetable and schedule set out the individual steps involved in the long-term disposal of radioactive waste in Austria. It provides clarity on the objectives, milestones and decisions throughout the entire final disposal process.

Current status

Following the submission of the Waste Management Advisory Board’s recommendations to the Federal Government, the waste management process has now entered the next implementation stage of the conceptual phase. The focus is now on defining a disposal solution, developing the site selection process and preparing the strategic and legal framework for the subsequent project phases.

The four stages of the final disposal process

Focus on the current phase

Phase 1

The project is currently in the preliminary and conceptual phase of radioactive waste management. During this stage, the technical, legal, economic and societal requirements for the long-term safe disposal of radioactive waste have already been established. To this end, existing principles have been analysed, safety requirements further developed and different interests and perspectives incorporated through public engagement processes. The findings will subsequently be incorporated into the development of an overall concept that defines the future type of final repository, the site selection process and the necessary legal framework. The aim of this phase is to update the National Waste Management Programme and to establish the legal basis for its further implementation.

The diagram below shows the milestones and work packages for Phase 1 of the radioactive waste management programme in Austria.

Key milestones in Phase 1

12 December 2023

1.1 Overview of the current situation

The overall picture of radioactive waste management in Austria is set out, and the technical, legal and organisational context is analysed.

 

Related work packages

1.1.1 Legal review

Analysis of the existing national and European legal frameworks and identification of the legal amendments required for the further implementation of the final disposal process.

1.1.2 Technical review

Survey of existing radioactive waste and development of initial safety objectives and safety criteria for long-term safe disposal. 

1.1.3 Requirements for public participation

Definition of the requirements for public participation, transparency and governance to ensure a transparent and trustworthy process

6 June 2024

1.2 Recommendation by the Advisory Board on the way forward

Drawing up key recommendations for the further development of the final repository process and preparing the next implementation steps. 

 

Related work packages

 

1.2.1 Technical framework

Development of the technical and safety-related principles for the assessment of potential waste disposal solutions.

1.2.2 Comparison of options for final disposal

Comparison and evaluation of different waste management and final disposal options as a basis for further decision-making. 

1.2.3 Economic framework

Analysis of the economic framework and assessment of the impacts of various waste management options.

1.2.4 Framework for public engagement

Development of a conceptual framework for the future provision of information to and engagement of relevant stakeholders and the public.

6 June 2027

1.3 Preliminary decision on the type of repository and next steps

This milestone lays the foundations for the selection of a disposal solution and for the further development of the site selection process.

Related work packages

1.3.1 Responsibilities and organisational structure

Definition of roles, responsibilities and organisational framework for the further implementation of the waste management programme. 

1.3.2 Launch of the public engagement strategy

Commencement of the implementation of the public engagement concept and establishment of initial public engagement measures. 

1.3.3 Specification of safety criteria and generic safety analysis

Further development of the safety criteria and carrying out an initial generic safety analysis as a basis for the assessment of possible waste management solutions. 

1.3.4 Draft of a generic site selection procedure

Development of an initial concept for a site-independent site selection procedure.

1.3.5 Detailed examination of final repository types

In-depth investigation of suitable types of final repositories and their requirements. 

1.3.6 Continuity in the waste management process

Development of measures to ensure the long-term preservation of knowledge, expertise and organisational continuity in the waste management process. 

12 December 2029

1.4 Resolution on the revised National Waste Management Programme

The results of the conceptual phase will be consolidated and incorporated into the updated National Waste Management Programme. 

Related work packages

1.4.1 Development of a catalogue of criteria

Development of a catalogue of criteria for the assessment of potential sites and the subsequent site selection. 

1.4.2 Procedure for site selection in Austria

Further development and refinement of the procedure for site identification and site selection in Austria. 

1.4.3 Knowledge management

Establishment of structures for the preservation, transfer and further development of relevant knowledge within the waste management process. 

1.4.4 Implementation of the public engagement concept

Implementation and further development of the planned public engagement measures. 

1.4.5 Revision of the National Waste Management Programme (NEP)

Incorporating the results achieved into the National Waste Management Programme and preparing its update.

1.4.6 Identification of new legal requirements

Identification and description of the legal and regulatory amendments required for the subsequent stages of the process.

6.2031

1.5 Entry into force of the legal basis

Establishment of the legal framework for the implementation of the next project phase and the site selection process.

 

Related work packages

1.5.1 Legislative process

Drafting and implementation of the necessary legal framework for the next phase of the waste management process.

1.5.2 Costs of site selection

Determination of the financial framework and resources required to carry out the site selection process. 

1.5.3 Public participation in the legislative process

Supporting the legislative process through transparent information and opportunities for relevant stakeholders and the public to participate.