Drawing up a timetable for the disposal of radioactive waste The timetable and schedule set out key milestones, performance indicators and deadlines for the individual stages of the final disposal process.
As part of its 2021–2025 mandate, the Waste Management Advisory Board drew up a timetable and roadmap for the long-term disposal of radioactive waste in Austria. The plan sets out key milestones, performance indicators and timeframes for the individual stages of the final disposal process, taking into account both international experience and the Austrian context.
The timetable and roadmap covers the entire process, from conceptual design through site selection and construction to the operation and closure of a final repository. It is divided into four phases:
- Phase I: Conceptual design (until 2033)
- Phase II: Site selection (until 2041)
- Phase III: Construction (until 2058)
- Phase IV: Operation and decommissioning (until 2082)
The first phase focuses on the development of waste management concepts, the formulation of a site selection procedure and the establishment of the necessary legal and organisational framework.
As important decisions are still pending, the timetable and schedule have been designed as a ‘living document’. The key milestones remain in place, whilst timeframes and individual procedural steps can be adapted to reflect new findings and developments.
Timetable & Process
This timetable and roadmap was drawn up by the Waste Management Advisory Board as part of its work between 2021 and 2025. Following its incorporation into the National Waste Management Programme, it forms the basis for the structured implementation of the next steps towards the long-term disposal of radioactive waste in Austria.
Go to the report on the timetable and roadmap
Go to the Timetable & Process
Recommendations of the Waste Management Advisory Board
4.1 Timetable and schedule
Observation: The current timetable and schedule set out a feasible but tight timeframe for the construction and operation of an Austrian final repository. In Phase 1 (concepts for final disposal) in particular, numerous fundamental and far-reaching decisions are scheduled to be taken within a tight timeframe.
Recommendation: The timetable and schedule, together with the key performance indicators, should be incorporated into the National Waste Management Programme and implemented.
4.2 Extension of the waste disposal contract
Observation: A realistic timeline shows that the construction and filling of the final repository cannot be completed by the time the waste management contract between the Federal Government, the municipality of Seibersdorf and NES expires in 2045. Furthermore, no decision has yet been taken on how radioactive waste will be conditioned once the final repository has been filled. When considering an extension, it should therefore be borne in mind that the treatment and interim storage of newly generated waste can continue to be carried out at the Seibersdorf site in the future.
Recommendation: The existing contract between the municipality of Seibersdorf, Nuclear Engineering Seibersdorf GmbH and the Republic of Austria, as set out in the timetable and schedule annexed to the report, should be extended.